NHBRC Inspection Stages: What Happens at Each Stage

Wakha Team 23 minitsi u vhala
NHBRC Inspection Stages: What Happens at Each Stage

Building a home in South Africa means navigating NHBRC inspection stages — mandatory quality checks that verify your construction meets minimum building standards. These inspections aren’t optional. They’re required by law under the Housing Consumers Protection Measures Act, and failing an inspection can halt your project until defects are rectified.

For builders and property developers, understanding NHBRC inspection stages is essential. Each stage has specific requirements, common failure points, and preparation steps that determine whether you pass or fail. A failed inspection doesn’t just delay your project — it can affect payment schedules, completion dates, and your ability to obtain occupation certificates.

This guide provides a detailed breakdown of each NHBRC inspection stage. We’ll cover what inspectors check, common defects found, how to prepare, timeline requirements, and what happens if you fail. We’ll also explain how construction management software can help you track inspection stages and ensure you’re always ready.

Overview of the NHBRC Inspection Process

The NHBRC conducts five mandatory inspections during residential construction. These inspections occur at critical stages of construction, verifying that work meets approved plans and minimum building standards before you proceed to the next stage.

The Five Inspection Stages

  1. Stage 1: Foundation — After excavation, before concrete pour
  2. Stage 2: Wall Plate — When walls are complete, before roof structure
  3. Stage 3: Roof Structure — After roof frame installation, before roof covering
  4. Stage 4: Practical Completion — When home is substantially complete
  5. Stage 5: Final Inspection — After all work is complete, before handover

Each stage must be passed before you can proceed to the next construction phase. Failing an inspection means rectifying defects and scheduling a re-inspection, which can delay your project by days or weeks.

Notification Requirements

You must notify the NHBRC at least 48 hours before each inspection stage. Notification can be done online through the NHBRC portal, by phone, or via email. The NHBRC will schedule an inspector to visit your site, typically within 2-3 business days of your request.

Important: Don’t proceed to the next construction stage until you’ve passed the current inspection. Proceeding without passing an inspection can result in penalties and may affect warranty coverage.

Inspection Timing and Scheduling

Plan your construction schedule around inspection stages. Delays in inspections can cascade through your project timeline, affecting completion dates and payment schedules. Build buffer time into your schedule for potential re-inspections.

Pro tip: Schedule inspections as soon as you’re ready. Don’t wait until the last minute — inspectors have busy schedules, and delays in inspection scheduling can delay your entire project.

Stage 1: Foundation Inspection

The foundation inspection is the first critical checkpoint. It occurs after foundation excavation is complete but before concrete is poured. This inspection verifies that foundation dimensions, depth, and preparation meet approved plans and building standards.

What the Inspector Checks

Foundation dimensions and depth:

  • Foundation width matches approved plans (typically 600mm for single-storey, 900mm for double-storey)
  • Foundation depth meets minimum requirements (typically 450mm below ground level, or as specified by geotechnical report)
  • Foundation is level and square (checking diagonals and levels)
  • Foundation alignment matches building layout on site

Soil conditions and geotechnical compliance:

  • Soil conditions are suitable for foundation construction
  • Geotechnical report requirements are met (if required)
  • Foundation is not in areas of poor soil or waterlogging
  • Site drainage is adequate to prevent water accumulation around foundations

Foundation reinforcement:

  • Reinforcement bars (rebar) are correctly positioned according to structural drawings
  • Rebar spacing matches specifications (typically 200mm centres)
  • Rebar is properly tied and secured
  • Rebar cover (concrete cover over reinforcement) meets minimum requirements (typically 50mm)

Foundation preparation:

  • Foundation trench is clean and free of debris
  • Foundation base is level and compacted
  • Formwork (if used) is correctly positioned and secure
  • No water accumulation in foundation trench

Site drainage:

  • Site drainage is adequate to prevent water from accumulating around foundations
  • Drainage channels are positioned correctly
  • Surface water will drain away from foundations

Common Defects Found at Foundation Stage

Incorrect foundation depth:

  • Foundation not deep enough (less than 450mm below ground level)
  • Foundation depth doesn’t match geotechnical report requirements
  • Foundation in areas of poor soil without proper treatment

Foundation dimension errors:

  • Foundation width narrower than approved plans
  • Foundation not square (diagonals don’t match)
  • Foundation alignment doesn’t match building layout

Reinforcement errors:

  • Rebar incorrectly positioned or missing
  • Rebar spacing incorrect (too wide or too narrow)
  • Insufficient rebar cover (concrete cover less than 50mm)
  • Rebar not properly tied or secured

Site drainage issues:

  • Inadequate site drainage causing water accumulation
  • Drainage channels not positioned correctly
  • Surface water draining toward foundations instead of away

Geotechnical compliance:

  • Missing geotechnical report when required
  • Foundation not complying with geotechnical report recommendations
  • Foundation in areas of expansive clay without proper treatment

How to Prepare for Foundation Inspection

Before excavation:

  • Review approved building plans and structural drawings
  • Check if geotechnical report is required (expansive clay, high water table, slopes)
  • Obtain geotechnical report if required
  • Mark foundation positions accurately on site

During excavation:

  • Excavate to correct depth (450mm minimum, or as per geotechnical report)
  • Ensure foundation width matches plans (600mm for single-storey, 900mm for double-storey)
  • Check foundation is square (measure diagonals)
  • Ensure foundation base is level and compacted
  • Remove any debris or water from foundation trench

Reinforcement installation:

  • Position rebar according to structural drawings
  • Ensure rebar spacing matches specifications (200mm centres)
  • Ensure rebar cover meets minimum requirements (50mm)
  • Tie rebar securely to prevent movement during concrete pour

Site drainage:

  • Ensure site drainage channels are positioned correctly
  • Verify surface water will drain away from foundations
  • Check for areas of water accumulation

Before inspection:

  • Clean foundation trench of debris
  • Remove any water accumulation
  • Verify all dimensions match approved plans
  • Ensure geotechnical requirements are met (if applicable)
  • Notify NHBRC at least 48 hours before inspection

Timeline Requirements

Foundation inspection should be scheduled:

  • After foundation excavation is complete
  • After reinforcement is installed
  • Before concrete is poured
  • Within 48 hours of notifying NHBRC (inspector will schedule visit)

Don’t pour concrete until foundation inspection is passed. Pouring concrete before passing inspection can result in penalties and may require foundation removal if defects are found.

What Happens If You Fail Foundation Inspection

If you fail foundation inspection, you’ll receive a report detailing defects that must be rectified. Common rectification requirements:

  • Depth issues — Excavate deeper if foundation not deep enough
  • Dimension errors — Adjust foundation width or alignment
  • Reinforcement errors — Reposition or add reinforcement bars
  • Drainage issues — Install or adjust site drainage
  • Geotechnical compliance — Address geotechnical requirements

You cannot pour concrete until defects are rectified and inspection is passed. The NHBRC will schedule a re-inspection once you’ve addressed the issues. Re-inspections typically occur within 2-3 business days.

Impact of failure: Foundation inspection failure can delay your project by 1-2 weeks, affecting your entire construction schedule and payment certificates.

Stage 2: Wall Plate Level Inspection

The wall plate inspection occurs when walls are complete and the wall plate (top plate) is installed, but before the roof structure is added. This inspection verifies that wall construction meets approved plans and building standards.

What the Inspector Checks

Wall dimensions and alignment:

  • Wall heights match approved plans
  • Wall lengths and positions match building layout
  • Walls are plumb (vertical) and level
  • Wall alignment is correct (walls square to each other)

Wall construction:

  • Brickwork or blockwork meets minimum standards
  • Mortar joints are properly filled and consistent
  • Wall construction method matches approved plans (brick, block, or other)
  • Wall thickness matches specifications

Wall plate installation:

  • Wall plate is correctly installed and level
  • Wall plate is properly secured to walls
  • Wall plate dimensions match structural requirements
  • Wall plate alignment is correct

Damp proofing:

  • Damp proof course (DPC) is installed correctly at base of walls
  • DPC is continuous and properly sealed
  • DPC height matches specifications (typically 150mm above ground level)
  • No gaps or damage in DPC

Window and door openings:

  • Window and door openings are correctly positioned
  • Opening dimensions match approved plans
  • Lintels are installed correctly above openings
  • Opening heights match specifications

Structural elements:

  • Load-bearing walls are correctly identified and constructed
  • Non-load-bearing walls meet minimum standards
  • Wall ties (if required) are correctly installed
  • Structural connections are sound

Common Defects Found at Wall Plate Stage

Wall dimension errors:

  • Wall heights don’t match approved plans
  • Wall positions don’t match building layout
  • Walls not plumb (out of vertical)
  • Walls not square to each other

Wall construction defects:

  • Poor brickwork or blockwork (uneven joints, gaps)
  • Mortar joints not properly filled
  • Wall construction doesn’t match approved method
  • Wall thickness incorrect

Wall plate errors:

  • Wall plate not level
  • Wall plate not properly secured
  • Wall plate dimensions incorrect
  • Wall plate alignment incorrect

Damp proofing issues:

  • Damp proof course missing or incorrectly installed
  • DPC not continuous (gaps or breaks)
  • DPC height incorrect (too low or too high)
  • DPC damaged or not properly sealed

Opening defects:

  • Window or door openings incorrectly positioned
  • Opening dimensions don’t match plans
  • Lintels missing or incorrectly installed
  • Opening heights incorrect

How to Prepare for Wall Plate Inspection

During wall construction:

  • Build walls to correct heights according to approved plans
  • Ensure walls are plumb and level
  • Verify wall positions match building layout
  • Check walls are square to each other
  • Use proper brickwork or blockwork techniques
  • Fill mortar joints properly

Wall plate installation:

  • Install wall plate level and square
  • Secure wall plate properly to walls
  • Verify wall plate dimensions match structural requirements
  • Check wall plate alignment

Damp proofing:

  • Install damp proof course at base of walls
  • Ensure DPC is continuous with no gaps
  • Verify DPC height (150mm above ground level)
  • Seal DPC properly at joints

Window and door openings:

  • Position openings according to approved plans
  • Verify opening dimensions match plans
  • Install lintels correctly above openings
  • Check opening heights

Before inspection:

  • Verify all dimensions match approved plans
  • Check walls are plumb and level
  • Ensure damp proofing is correctly installed
  • Verify window and door openings are correct
  • Notify NHBRC at least 48 hours before inspection

Timeline Requirements

Wall plate inspection should be scheduled:

  • After walls are complete
  • After wall plate is installed
  • Before roof structure is installed
  • Within 48 hours of notifying NHBRC

Don’t install roof structure until wall plate inspection is passed. Installing roof structure before passing inspection can result in penalties and may require removal if defects are found.

What Happens If You Fail Wall Plate Inspection

If you fail wall plate inspection, you’ll receive a report detailing defects that must be rectified. Common rectification requirements:

  • Wall dimension errors — Adjust wall heights or positions
  • Construction defects — Repair brickwork or blockwork
  • Wall plate errors — Adjust or reinstall wall plate
  • Damp proofing issues — Install or repair damp proof course
  • Opening defects — Adjust openings or install lintels

You cannot install roof structure until defects are rectified and inspection is passed. The NHBRC will schedule a re-inspection once you’ve addressed the issues.

Impact of failure: Wall plate inspection failure can delay your project by 1-2 weeks, affecting your construction schedule and payment certificates.

Stage 3: Roof Structure Inspection

The roof structure inspection occurs after the roof frame is installed but before roof covering is applied. This inspection verifies that the roof structure matches approved plans and meets structural requirements.

What the Inspector Checks

Roof structure dimensions:

  • Roof structure matches approved plans
  • Roof pitch (slope) is correct
  • Roof dimensions match building footprint
  • Roof structure is square and level

Roof trusses or beams:

  • Roof trusses or beams are correctly installed
  • Truss spacing matches specifications (typically 900mm or 1200mm centres)
  • Trusses are properly secured to wall plate
  • Truss connections are sound

Structural bracing:

  • Roof structure is adequately braced
  • Bracing prevents lateral movement
  • Bracing is correctly positioned and secured
  • Structural connections are sound

Roof pitch and dimensions:

  • Roof pitch matches approved plans
  • Roof dimensions match building footprint
  • Roof overhangs are correct
  • Roof structure is level

Structural connections:

  • Connections between trusses and wall plate are sound
  • Connections between truss members are properly made
  • Structural fixings are correctly installed
  • No loose or missing connections

Common Defects Found at Roof Structure Stage

Roof structure dimension errors:

  • Roof structure doesn’t match approved plans
  • Roof pitch incorrect
  • Roof dimensions don’t match building footprint
  • Roof structure not square or level

Truss installation errors:

  • Trusses incorrectly spaced (too wide or too narrow)
  • Trusses not properly secured to wall plate
  • Truss connections loose or incorrect
  • Missing or damaged trusses

Bracing issues:

  • Insufficient bracing
  • Bracing incorrectly positioned
  • Bracing not properly secured
  • Structural connections loose

Roof pitch errors:

  • Roof pitch doesn’t match approved plans
  • Roof pitch too steep or too shallow
  • Inconsistent roof pitch across structure

Connection defects:

  • Loose connections between trusses and wall plate
  • Loose connections between truss members
  • Missing or incorrect structural fixings
  • Damaged connections

How to Prepare for Roof Structure Inspection

During roof structure installation:

  • Install roof structure according to approved plans
  • Ensure roof pitch matches plans
  • Verify roof dimensions match building footprint
  • Check roof structure is square and level
  • Install trusses at correct spacing (900mm or 1200mm centres)
  • Secure trusses properly to wall plate

Structural bracing:

  • Install adequate bracing to prevent lateral movement
  • Position bracing correctly
  • Secure bracing properly
  • Verify structural connections are sound

Before inspection:

  • Verify roof structure matches approved plans
  • Check roof pitch is correct
  • Ensure trusses are properly secured
  • Verify bracing is adequate
  • Check all structural connections are sound
  • Notify NHBRC at least 48 hours before inspection

Timeline Requirements

Roof structure inspection should be scheduled:

  • After roof frame is installed
  • After structural bracing is installed
  • Before roof covering is applied
  • Within 48 hours of notifying NHBRC

Don’t apply roof covering until roof structure inspection is passed. Applying roof covering before passing inspection can result in penalties and may require removal if defects are found.

What Happens If You Fail Roof Structure Inspection

If you fail roof structure inspection, you’ll receive a report detailing defects that must be rectified. Common rectification requirements:

  • Dimension errors — Adjust roof structure dimensions or pitch
  • Truss installation errors — Reposition or secure trusses correctly
  • Bracing issues — Install or adjust structural bracing
  • Connection defects — Repair or replace structural connections

You cannot apply roof covering until defects are rectified and inspection is passed. The NHBRC will schedule a re-inspection once you’ve addressed the issues.

Impact of failure: Roof structure inspection failure can delay your project by 1-2 weeks, affecting your construction schedule and payment certificates.

Stage 4: Practical Completion Inspection

The practical completion inspection occurs when the home is substantially complete — all major work is finished, but minor finishing items may remain. This is often the most critical inspection, as it determines whether the home is ready for occupation.

What the Inspector Checks

General compliance:

  • Home matches approved building plans
  • All structural elements are complete
  • Workmanship meets minimum building standards
  • No major defects or incomplete work

Electrical installations:

  • Electrical installations are complete and compliant
  • Electrical certificate of compliance (COC) is available
  • All electrical work meets SANS 10142 standards
  • Electrical installations are safe and functional

Plumbing installations:

  • Plumbing installations are complete and compliant
  • Plumbing certificate is available (if required by municipality)
  • All plumbing work meets building standards
  • Plumbing installations are functional and leak-free

Windows and doors:

  • Windows and doors are installed and functional
  • Windows and doors meet specifications
  • Glazing is correct and secure
  • Door and window hardware is functional

Roof covering:

  • Roof covering is complete and weatherproof
  • Roof covering matches approved plans
  • No leaks or defects in roof covering
  • Roof flashings are correctly installed

External finishes:

  • External wall finishes are complete
  • Paint or render is applied (if specified)
  • External finishes meet minimum standards

Internal finishes:

  • Internal wall finishes are substantially complete
  • Floor finishes are complete (or ready for final finishes)
  • Ceiling finishes are complete
  • Internal finishes meet minimum standards

Services:

  • Water supply is connected and functional
  • Sanitation is connected and functional
  • Electrical supply is connected and functional
  • All services are operational

Common Defects Found at Practical Completion Stage

Structural defects:

  • Structural elements incomplete or defective
  • Cracks in walls or foundations
  • Structural elements don’t meet building standards

Electrical defects:

  • Electrical installations incomplete or non-compliant
  • Missing electrical certificate of compliance
  • Electrical work doesn’t meet SANS 10142 standards
  • Unsafe electrical installations

Plumbing defects:

  • Plumbing installations incomplete or non-compliant
  • Leaks in plumbing systems
  • Plumbing work doesn’t meet building standards
  • Missing plumbing certificates

Window and door defects:

  • Windows or doors not installed or functional
  • Windows or doors don’t meet specifications
  • Glazing incorrect or insecure
  • Door and window hardware not functional

Roof covering defects:

  • Roof covering incomplete or defective
  • Leaks in roof covering
  • Roof flashings incorrectly installed
  • Roof covering doesn’t match approved plans

Finish defects:

  • External or internal finishes incomplete
  • Finishes don’t meet minimum standards
  • Poor workmanship in finishes

Service defects:

  • Water supply not connected or functional
  • Sanitation not connected or functional
  • Electrical supply not connected or functional
  • Services not operational

How to Prepare for Practical Completion Inspection

Before inspection:

  • Complete all major structural work
  • Complete electrical installations and obtain COC
  • Complete plumbing installations and obtain certificates
  • Install all windows and doors
  • Complete roof covering and ensure it’s weatherproof
  • Complete external and internal finishes (or ensure they’re ready)
  • Connect all services and ensure they’re functional
  • Verify home matches approved building plans
  • Ensure workmanship meets minimum standards
  • Notify NHBRC at least 48 hours before inspection

Documentation:

  • Have electrical certificate of compliance available
  • Have plumbing certificates available (if required)
  • Have approved building plans available
  • Have NHBRC enrolment certificate available

Timeline Requirements

Practical completion inspection should be scheduled:

  • After all major work is complete
  • After electrical and plumbing installations are complete
  • After services are connected
  • Before occupation certificate is issued
  • Within 48 hours of notifying NHBRC

Don’t obtain occupation certificate until practical completion inspection is passed. Municipal authorities may require NHBRC practical completion approval before issuing occupation certificates.

What Happens If You Fail Practical Completion Inspection

If you fail practical completion inspection, you’ll receive a report detailing defects that must be rectified. Common rectification requirements:

  • Structural defects — Repair structural elements
  • Electrical defects — Complete or repair electrical installations
  • Plumbing defects — Complete or repair plumbing installations
  • Window and door defects — Install or repair windows and doors
  • Roof covering defects — Complete or repair roof covering
  • Finish defects — Complete or repair finishes
  • Service defects — Connect or repair services

You cannot obtain an occupation certificate or hand over the home until defects are rectified and inspection is passed. The NHBRC will schedule a re-inspection once you’ve addressed the issues.

Impact of failure: Practical completion inspection failure can delay handover by 2-4 weeks, affecting payment schedules and client relationships.

Stage 5: Final Inspection

The final inspection occurs after the home is fully complete and all finishing work is done. This is typically the last inspection before handover, verifying that the home is ready for occupation.

What the Inspector Checks

Completion:

  • All work is complete to a satisfactory standard
  • No outstanding defects or incomplete work
  • All finishing work is complete
  • Home is ready for occupation

Quality:

  • Workmanship meets minimum building standards
  • No major defects or issues
  • All finishes are complete and satisfactory
  • Home is in good condition

Certificates:

  • All required certificates are in place
  • Electrical certificate of compliance is available
  • Plumbing certificates are available (if required)
  • Other required certificates are available

Handover readiness:

  • Home is ready for handover to homebuyer
  • All defects from previous inspections are rectified
  • No outstanding issues

Common Defects Found at Final Inspection

Outstanding work:

  • Incomplete finishing work
  • Outstanding defects from previous inspections
  • Work not completed to satisfactory standard

Quality issues:

  • Poor workmanship
  • Defects in finishes
  • Issues with installations

Missing certificates:

  • Missing electrical certificate of compliance
  • Missing plumbing certificates
  • Missing other required certificates

Defects:

  • Defects not rectified from previous inspections
  • New defects discovered
  • Issues affecting occupation

How to Prepare for Final Inspection

Before inspection:

  • Complete all finishing work
  • Rectify all defects from previous inspections
  • Ensure workmanship meets minimum standards
  • Obtain all required certificates
  • Verify home is ready for occupation
  • Notify NHBRC at least 48 hours before inspection

Documentation:

  • Have all required certificates available
  • Have NHBRC enrolment certificate available
  • Have approved building plans available
  • Have documentation of rectified defects

Timeline Requirements

Final inspection should be scheduled:

  • After all work is complete
  • After all defects are rectified
  • After all certificates are obtained
  • Before handover to homebuyer
  • Within 48 hours of notifying NHBRC

Don’t hand over the home until final inspection is passed. Handing over before passing inspection can affect warranty coverage and may result in penalties.

What Happens If You Fail Final Inspection

If you fail final inspection, you’ll receive a report detailing defects that must be rectified. Common rectification requirements:

  • Outstanding work — Complete finishing work
  • Quality issues — Repair defects or improve workmanship
  • Missing certificates — Obtain required certificates
  • Defects — Rectify outstanding defects

You cannot hand over the home until defects are rectified and inspection is passed. The NHBRC will schedule a re-inspection once you’ve addressed the issues.

Impact of failure: Final inspection failure can delay handover by 1-2 weeks, affecting payment schedules and client relationships.

What Happens If You Fail an Inspection

Failing an NHBRC inspection means you cannot proceed to the next construction stage until defects are rectified and the inspection is passed. Here’s what happens:

Inspection Failure Process

  1. Inspection report — Inspector provides a written report detailing defects
  2. Rectification period — You have a specified period to rectify defects (typically 7-14 days)
  3. Re-inspection — NHBRC schedules a re-inspection once defects are rectified
  4. Approval — Once defects are rectified and inspection is passed, you can proceed

Impact of Inspection Failures

Project delays:

  • Failed inspections delay your construction schedule
  • Re-inspections typically occur within 2-3 business days
  • Rectification work can take days or weeks
  • Delays cascade through your project timeline

Cost impact:

  • Rectification work adds costs
  • Delays increase site overheads
  • Payment certificates may be delayed
  • Client relationships may be affected

Compliance impact:

  • Multiple failures may affect your NHBRC registration
  • Failures are recorded in NHBRC database
  • May affect future project approvals

Preventing Inspection Failures

Preparation:

  • Review inspection requirements before each stage
  • Ensure work meets approved plans and building standards
  • Address common defects proactively
  • Have all required documentation ready

Quality control:

  • Implement quality control processes
  • Check work before requesting inspection
  • Address defects immediately
  • Use inspection checklists

Communication:

  • Notify NHBRC promptly (48 hours before inspection)
  • Communicate with inspectors clearly
  • Address inspector concerns immediately
  • Follow up on inspection results promptly

How Wakha Tracks Inspection Stages and Deadlines Automatically

Managing NHBRC inspection stages manually — tracking deadlines, scheduling inspections, managing documents, and monitoring compliance — is time-consuming and error-prone. Construction management software like Wakha automates these workflows, ensuring you never miss an inspection deadline or compliance requirement.

Automated Inspection Stage Tracking

Wakha’s NHBRC compliance module automatically tracks inspection stages for each home:

Stage reminders:

  • Automated reminders for each inspection stage
  • Alerts when inspection deadlines are approaching
  • Notifications when stages are ready for inspection
  • Calendar integration for inspection scheduling

Stage workflows:

  • Workflow templates for each inspection stage
  • Checklists for stage preparation
  • Document requirements for each stage
  • Status tracking across all projects

Deadline management:

  • Automatic calculation of inspection deadlines based on construction schedule
  • Alerts when deadlines are approaching
  • Tracking of missed deadlines
  • Integration with project timeline

Inspection Scheduling and Management

Wakha helps you schedule and manage inspections:

Scheduling:

  • Integration with NHBRC portal for inspection requests
  • Calendar view of all scheduled inspections
  • Reminders before inspection dates
  • Rescheduling capabilities

Document management:

  • Store inspection reports and certificates
  • Upload photos and documents for each inspection
  • Version control for inspection documents
  • Document sharing with inspectors

Status tracking:

  • Track inspection status across all projects
  • See which inspections are pending, scheduled, or passed
  • Identify projects with failed inspections
  • Monitor re-inspection requirements

Preparation Checklists

Wakha provides preparation checklists for each inspection stage:

Foundation inspection checklist:

  • Foundation dimensions verified
  • Reinforcement correctly positioned
  • Site drainage adequate
  • Geotechnical requirements met

Wall plate inspection checklist:

  • Walls plumb and level
  • Wall plate correctly installed
  • Damp proofing installed
  • Openings correctly positioned

Roof structure inspection checklist:

  • Roof structure matches plans
  • Trusses correctly installed
  • Bracing adequate
  • Connections sound

Practical completion checklist:

  • All major work complete
  • Electrical and plumbing certificates obtained
  • Services connected
  • Finishes complete

Final inspection checklist:

  • All work complete
  • All defects rectified
  • All certificates obtained
  • Home ready for handover

Failed Inspection Management

Wakha helps you manage failed inspections:

Defect tracking:

  • Record defects from inspection reports
  • Track rectification progress
  • Monitor re-inspection scheduling
  • Document rectification completion

Impact analysis:

  • See how failed inspections affect project timeline
  • Calculate cost impact of delays
  • Identify trends across projects
  • Prevent repeat failures

Integration with Project Management

Wakha’s NHBRC module integrates seamlessly with project management:

Timeline integration:

  • Inspection stages appear as milestones in project timeline
  • Failed inspections automatically adjust timeline
  • Inspection delays cascade through schedule
  • Payment certificate dates linked to inspection stages

Budget integration:

  • Inspection costs tracked in project budget
  • Re-inspection costs included in budget
  • Compliance costs reflected in budget
  • Cost impact of delays visible

Site diary integration:

  • Link inspection photos to site diary entries
  • Record inspection notes in site diary
  • Track inspection-related activities
  • Document preparation work

Real-World Benefits

Using Wakha for NHBRC inspection tracking delivers tangible benefits:

  • Never miss a deadline — Automated reminders ensure you schedule inspections on time
  • Better preparation — Checklists help ensure you’re ready for each inspection
  • Higher pass rates — Better preparation leads to fewer failed inspections
  • Faster handover — Streamlined workflows reduce delays in obtaining occupation certificates
  • Better record-keeping — All inspection documents stored in one place

Getting Started with Wakha

Wakha’s NHBRC compliance module is available on the Developer plan (R6,999/month). The module includes:

  • Automated inspection stage tracking and reminders
  • Inspection scheduling and calendar integration
  • Preparation checklists for each stage
  • Document management for inspection reports and certificates
  • Failed inspection management and defect tracking
  • Integration with project timeline and budget

To see how Wakha can streamline your NHBRC inspection workflows, request a demo or explore Wakha’s features.

Frequently Asked Questions

How far in advance should I notify NHBRC for an inspection?

You must notify NHBRC at least 48 hours before each inspection stage. However, it’s best practice to notify as soon as you’re ready — inspectors have busy schedules, and early notification helps ensure inspections are scheduled promptly.

What happens if I miss an inspection deadline?

Missing an inspection deadline can delay your project. You should notify NHBRC as soon as possible and schedule the inspection. However, proceeding to the next construction stage without passing the current inspection can result in penalties and may affect warranty coverage.

Can I proceed with construction while waiting for inspection?

You can continue with work that doesn’t affect the inspection stage. For example, while waiting for foundation inspection, you can continue with site setup or material ordering, but you cannot pour concrete until foundation inspection is passed.

What if the inspector doesn’t arrive on the scheduled date?

If the inspector doesn’t arrive on the scheduled date, contact NHBRC immediately. They will reschedule the inspection. Document the delay and its impact on your project timeline.

How long does it take to get inspection results?

Inspection results are typically provided immediately after the inspection. The inspector will provide a verbal indication of pass or fail, followed by a written report within 1-2 business days.

Can I dispute an inspection failure?

Yes. If you believe an inspection failure is incorrect, you can contact NHBRC to discuss the issue. However, you must still rectify defects before proceeding. Disputes are typically resolved through discussion with NHBRC, but you cannot proceed without passing inspection.

What if I need to change my construction schedule?

If your construction schedule changes, update your inspection schedule accordingly. Notify NHBRC of any changes to inspection dates. Wakha’s timeline integration automatically adjusts inspection reminders when your schedule changes.

Conclusion

NHBRC inspection stages are mandatory milestones in residential construction. Understanding what inspectors check at each stage, common defects, and how to prepare helps ensure you pass inspections on the first attempt, avoiding delays and costs.

Each inspection stage has specific requirements — foundation depth and reinforcement, wall plate installation and damp proofing, roof structure and bracing, practical completion and services, final inspection and handover readiness. Failing any inspection means rectifying defects and scheduling re-inspections, which can delay your project by days or weeks.

For builders managing multiple projects, tracking inspection stages manually is time-consuming and error-prone. Construction management software like Wakha automates inspection stage tracking, provides preparation checklists, manages inspection scheduling, and integrates compliance with project management workflows.

If you’re building homes in South Africa, NHBRC inspections aren’t optional — they’re essential. Prepare properly for each stage, address defects immediately, and use tools that help you track deadlines and ensure compliance. Your project timeline, your profitability, and your reputation depend on it.